Project Title & Location
I-5 HOV - Port of Tacoma Rd. I/C to King County Line
|
Project Description
This project builds HOV lanes on I-5 from the Port of Tacoma Road to the Pierce/King County line. There are currently eight lanes of traffic and there will be 10 lanes when the project is complete.
|
|
Contractor/Consultant
Project not yet advertised or awarded
|
|
Recent Progress
A consultant, CH2M Hill, has been hired to develop the wetland mitigation plan and to develop plans for the site restoration. This design work is underway and is scheduled to be completed spring 2006.
|
|
Design Construction Impacts
No issues at this time.
|
|
Environmental Impacts / Compliance
Right of way acquisitions for storm water treatment facilities are underway and are to be completed soon.
|
Impacts to Traffic
Temporary impacts during construction could include narrow lanes along with nighttime lane closures and minor detours at the 54th Avenue Interchange.
|