Recent Progress
Recent progress includes acquisition of the needed property for the wetland mitigation site for this project. Also, the region is working towards acquiring the needed right-of-way for stormwater treatment facilities by this summer. This would complete all acquisitions needed for this project.
Other recent accomplishments include completion of the 90 percent bridge plans and provisions.
Currently the hydraulic plans and provisions are scheduled to be completed this spring.
|