I-5 - Port of Tacoma Road Interchange to King County Line - HOV Lanes

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location
I-5 HOV - Port of Tacoma Rd. I/C to King County Line

Project Description
This project builds HOV lanes on I-5 from the Port of Tacoma Road to the Pierce/King County line. There are currently eight lanes of traffic and there will be 10 lanes when the project is complete.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress

WSDOT has partnered with the City of Federal Way to develop a project that will create and restore wetland and stream areas along West Hylebos Creek to mitigate for impacts from the I-5 widening project.  This will be a seperate project constructed before the I-5 widening.  Both WSDOT and Federal Way have hired a consultant, CH2Mhill, to design the project and develop plans for the mitigation site and to construct a new bridge on S. 373rd St. to accommodate a stream relocation and improve fish and wildlife passage.

 

Currently the wetland restoration project is in the design stage and work to finalize the design and develop plans is scheduled for this winter.

 

Design Construction Impacts

No issues at this time.

Environmental Impacts / Compliance

Work to construct the Spring Valley Restoration Project site could begin as early as Summer of 2007.

Impacts to Traffic
Temporary impacts during construction could include narrow lanes along with nighttime lane closures and minor detours at the 54th Avenue Interchange.

Project Milestones Scheduled Attained Milestone Outlook
Hydraulic and Storm water Redesign August 2004 October 2004 The storm water and hydraulic design are complete.
Environmental Documentation Complete October 2006   No issues at this time.
Right of Way acquisition complete June 2005   Needed right of way for storm water treatment facilities is in the appraisal stage and is scheduled to be acquired soon.
Advertisement Date January 2009   No issues at this time.
Open to traffic October 2011   No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  4.4  11.6%
Right-of-Way $  6.6  17.4%
Construction $27.0  71.0%
Funded Project Costs $38.0 100.0%

Nickel funds included in above costs

$33.6 88.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Steve Fuchs, Project Engineer, (360) 570-6602, fuchss@wsdot.wa.gov