I-5 - Port of Tacoma Road Interchange to King County Line - HOV Lanes

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
I-5 Port of Tacoma Road Interchange to King County Line

Project Description
This project builds HOV lanes on I-5 from the Port of Tacoma Road to the Pierce/King County line. There are currently eight lanes of traffic and there will be 10 lanes when the project is complete.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The Tacoma/Pierce County HOV Office is developing the plans for approval for the Port of Tacoma Road to King County Line Project. All needed existing topographical information has been collected. Geotech explorations will begin in mid-July for soil reconnaissance to commence preliminary structural and hydraulics design. 

The Port of Tacoma Road to King County Line project includes a smaller project, Spring Valley Restoration project. For this project, WSDOT partnered with the City of Federal Way to develop a project that will create and restore wetland and stream areas along West Hylebos Creek to mitigate for impacts from the I-5 widening project. The project includes a mitigation site and construction of a new bridge on S. 373rd St. to accommodate a stream relocation and improve fish and wildlife passage. The wetland restoration project was awarded February 22, 2007 to Mid Mountain Contractors, Inc. of Kirkland, WA. 

Design Construction Impacts
No issues at this time

Environmental Impacts / Compliance

Work to construct the Spring Valley Restoration Project site could begin as early as Summer 2007.

Impacts to Traffic
Temporary impacts during construction could include narrow lanes along with nighttime lane closures and minor detours at the 54th Avenue Interchange.

Project Milestones Scheduled Attained Milestone Outlook
Begin preconstruction engineering March 9, 1995 Plans for approval scheduled to be submitted.
Environmental Documentation Complete November 11, 1998   Informal consultation and NEPA DCE likely. Biological assessment in progress. Storm water/flood plain mitigation in progress.
Right of Way Certification Deember 20, 2008 August 2006 May need additional right of way due to new flood-plain mapping.
Advertisement Date January 20, 2009   No issues at this time.
Open to traffic June 20, 2012   No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  9.00  17.9%
Right-of-Way $ 4.53  9.0%
Construction $36.68  73.1%
Funded Project Costs $50.21 100.0%

Nickel funds included in above costs

$44.4 88.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Gordon Roycroft, HOV Project Manager (360) 709-8130, roycrog@wsdot.wa.gov