Design Construction Impacts
Utility relocation work is ongoing and is to be coordinated to with the contractor:
City of Tacoma Power - the power relocation work included nine separate projects - six of which have been complete. COT had to acquire several easements which took considerably longer then expected, but all easement issues have been resolved. There are three pending jobs - one should be completed in September, the remaining two are being scheduled for City of Tacoma crews. Qwest and Comcast will follow Tacoma Power's relocation on the poles.
City of Tacoma Water - all advance work is complete. The final work is to be coordinated and performed in conjunction with the Delin structure demolition work.
Puget Sound Energy - The final work is to be coordinated and performed in conjunction with the Delin structure demolition work.
|