I-5 - HOV Improvements - S 48th Street to Pacific Ave

Quarterly Project Report Update for Quarter Ending March 2007

Project Title & Location
I-5 HOV - South 48th Street to Pacific Avenue, Tacoma

Project Description
Improves safety on I-5, from 38th Street to I-705 by adding a collector-distributor lane for safer merges on and off the freeway.

Contractor/Consultant
Kiewit Pacific Co.

Recent Progress
Both north and southbound traffic has been shifted for the next phases of bridge demolition; demolition is expected to finish in spring 2007. Phase 2 of bridge demolition is complete, work is continuing on the artistic noise barrier walls along northbound I-5 and the artistic wall panels between M St and SR 16.

The base lifts of asphalt paving are complete on the new ramps and new collector-distributor. 


Repairs to the storm water and sewer systems under the Yakima Pond from the November storms are complete. The work was performed by the City of Tacoma.

Design Construction Impacts

The Project Office and Contractor have worked through issues regarding soil stability during soil nail wall construction and drainage tie-ins to the City of Tacoma system. 

The Project Office is monitoring potential utility conflicts with the remaining structure and drainage work.

Environmental Impacts / Compliance

Noise barrier walls are being constructed to minimize the effects of traffic noise on adjacent residences and schools.

Storm water detention ponds have been constructed for use as part of the contractor’s temporary erosion control measures. They will later be modified for permanent water quantity and quality treatment to accommodate the widened roadway.


Water quality is monitored to ensure that turbidity and pH thresholds are not exceeded at discharge points. 

To ensure compliance with all permits and regulations, on-site meetings are conducted with the Department of Ecology bi-monthly and with the City of Tacoma quarterly.

Impacts to Traffic

The northbound lanes have been shifted to the collector-distributor and the southbound lanes to the old northbound lanes to facilitate the demolition of the Yakima, Delin, and Tacoma Avenue bridges. Getting southbound traffic around bridge-demolition work required a major shift – a fairly dramatic detour into the regular northbound lanes. Drivers will negotiate sharp curves getting in and out of the detour prompting WSDOT to lower the speed limit to a cautionary 45 mph on the mile-long stretch. These traffic revisions are required to get drivers safely around the bridge demolition work and get this safety and mobility project completed.

Drivers also should be aware of an extended barrier between the southbound mainline and the merge lane from downtown Tacoma. The barrier severely reduces the time drivers will have to merge left to the mainline from downtown, against the grain of mainline drivers maneuvering right to exit at State Route 16 or South 38th Street.

Motorists can expect periodic nighttime lane closures on northbound and southbound I-5 throughout the project limits.

 

Electronic message signs and highway advisory radios (HARs) will be deployed throughout the area to alert travelers about traffic conditions and lane closures during construction.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertisement October 2004 March 2005  
Contract Award June 2005 June 2005  
Start Construction August 2005 August 2005  
Yakima/Delin  Bridges Open To Traffic Spring 2008    
Open To Traffic February 2008   Construction is expected to be completed by late Spring 2008.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $    5.8     5.6%
Right-of-Way $    3.2     3.1%
Construction $  94.8   91.3%
Funded Project Costs $103.8 100.0%

Nickel funds included in above costs

$  95.8  92.2%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Howard Diep, Project Engineer, (253) 589-6100