WSDOT Projects

text size: T T T

I-5 - HOV Improvement South 48th Street to Pacific Avenue - Construction Photos

2007
Column cages for the Yakima Avenue bridge are now in place

Column cages for the Yakima Avenue bridge are now in place. Each of the two new bridges will supported in the center by four columns.


The first concrete column is complete. A crane is used to lift the form off the finished column.




 A 300-ton hydraulic crane lifts steel girders into place for the new Yakima Ave overpass.  Each bridge will be built with 12 girders.  Individual girders weigh as much as 75 tons and are as long as 159 feet.  Watch time-lapse video of girder-setting.



Crews weave 4-by-6 carrier beams and stringers across the bridge girders before laying out the plywood sheets that serve as the floor for the concrete deck.

Green epoxy-coated re-bar is built into the structure of the new Yakima Avenue overpass.
Installing the green epoxy-coated re-bar is one of the final steps before the decks are paved.

Crews completed the first deck pour for the new Yakima Avenue overpass on Nov. 20, 2007.
On Nov. 20, 2007, crews began paving the deck of the new Yakima Avenue overpass. The yellow machine in the background is a Bidwell finisher, which is used to create a smooth, consistent surface.

May 2007

Crews (May 14) are building the forms for the abutment wall for the new Yakima Avenue bridge.



May 2007
On May 7, crews poured the footings for the new Yakima Avenue bridge over Interstate 5 in downtown Tacoma.
Cews pour the concrete footing for the new Yakima Avenue Bridge (May 7, 2007).



Aerial Photos/Southbound Shift in Place  April 2007









48th_aerial photo 1

With the northbound shift in place, crews prepare the middle lanes for the southbound shift.
With the northbound shift in place, crews prepare for the southbound shift.


Demolition Photos, February/March 2007
Most of the bridge demolition work is done at night to minimize traffic impacts.
Crews water down the demolition area to control dust.


Tacoma Avenue bridge with exposed rebar on south end.

A temporary column, or "bent," provides support while an excavator crunches through the bridge decks and rips through the rebar.

Crews continue to demolish three bridges over I-5 in downtown Tacoma. This is a shot of two bridges during the day, with T-Dome in background.  
The Tacoma Avenue and Delin Street bridges are ready for the next phase of demolition, which shifts southbound traffic into the regular northbound lanes.

On Feb. 7, 2007, crews began the second stage of demolition of the bridges over I-5. Here, Jeff Johnson uses an excavator with a hydraulic breaker to knock down the Tacoma Avenue Bridge.

On Feb. 7, 2007, crews began the second stage of demolition of the bridges over I-5. Here, Jeff Johnson uses an excavator with a hydraulic breaker to pound away at the Tacoma Avenue Bridge.


Construction Photos, December 2006
The new northbound collector-distributor lanes that will serve as a detour route during bridge demolition -- starting Jan. 20, 2007.
The new northbound collector-distributor lanes are nearing completion. Starting Jan. 20, these lanes will serve as the northbound detour during bridge-demolition work scheduled through fall 2007.




Construction Photos, October 2006

Crews continue to spread layers of dirt, as they elevate the ground between I-5 and South Tacoma Way. Workers are laying the groundwork for a new I-5 connection to a new Valley Valley viaduct.

Crews continue to spread layers of dirt to elevate the ground between I-5 and South Tacoma Way. Workers are laying the groundwork for revised I-5 connections to a new Nalley Valley viaduct.

In early October 2006, crews paved the new collector-distributor lanes on northbound I-5 through downtown Tacoma.

Crews pave the new collector-distributor lanes that will eliminate the weaving traffic on northbound I-5 between the SR 16 curve and I-705.


Construction Photos, August - September 2006

Workers construct the foundation for the bridge deck section of the new collector-distributor lanes over M Street.

Workers construct the foundation for the M Street bridge deck section of the new collector-distributor lanes that will ease congestion through downtown Tacoma.



This drainage structure is being installed between northbound I-5 and the off-ramp to SR 705 and SR 7. The structure will be used to retain storm drainage during major storm events.

This 10-foot-diameter drainage structure was installed between the northbound I-5 lanes and the off-ramp to SR 705/SR 7. A crane lifted the 22, 20-foot-long sections into place.

Construction Photos March 2006
Construction Photo Cutline Below

The road northbound I-5 travelers will use to reach westbound State Route 16 takes shape in the photo above. Crews are currently using the road to access work sites farther along I-5. Also pictured is a rebar cage crews will use for bridge shafts on the new M Street overpass.


Construction Photo Cutline Below
Above, work is progressing on the new ramp from northbound I-5 to I-705. Once the ramp is open to traffic, it separates traffic heading to I-705/downtown Tacoma from traffic merging on northbound I-5 from State Route 16. The large piece of machinery has begun to excavate for placement of the bridge supports.

Construction Photo Cutline Below
A worker from the contractor working on I-5 in the Tacoma area checks a bridge support reinforcement for the bridge over M street that will handle I-5 northbound traffic exiting to I-705.

Construction Photo Cutline Below
When excavating for new highway, crews many times build retaining walls. This wall is a soldier pile wall characterized by vertical beams connected by wooden supports. The wall is currently under construction on the east side of I-5 in the Tacoma Mall area.

Construction Photo Cutline Below
Along the portion of the I-5 project in Tacoma pictured above, crews complete a different type of retaining wall. This soil nail wall uses soil reinforced with soil nails, which are circled above. When the wall is complete, these nails will not be visible.

Construction Photo Cutline Below
Above, another photo of a soil nail wall with the nails highlighted. This type of retaining wall is being built along the east side of I-5 near Tacoma Mall.