I-90 - Two-Way Transit and HOV Operations - Construction Photos




April 2008 - Crews have begun to pour the concrete deck for the new direct access ramp from westbound I-90 to 80th Ave SE.


April 2008 - Crews are making progress building the bridge deck of the new ramp to 80th Avenue SE. Here crews are walking on top of the reinforcing rebar.


April 2008 - Crews continue working in the median between westbound I-90 and the center reversible roadway to install water lines for a fire protection system.


March 2008 - Crews are using large machines to crush the concrete barriers that previously separated westbound I-90 and the center reversible roadway.


March 2008 - Crews are working in the median between westbound I-90 and the center roadway to excavate and install water lines.

caption below photo
Feb. 2008 - Crews continue to build the new HOV off-ramp from westbound I-90 to 80th Avenue SE.

caption below photo
Feb. 2008 - These wooden planks are the first step in building the road surface. Crews will add wooden boards, rebar and concrete to complete the structure.

caption under photo
Feb. 2008 - Crews are installing the electrical work for new lamps along the right shoulder of westbound I-90.

caption under photo
Feb. 2008 - Crews are working to install irrigation lines along the right shoulder of westbound I-90 on Mercer Island.