I-90 - Highline Canal to Elk Heights - Complete August 2004

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location

I-90/Highline Canal to Elk Heights –


East of Cle Elum

Project Description
This project constructs a new truck climbing/passing lane on Interstate 90 eastbound from Highline Canal to Elk Heights, to reduce accidents from slower moving vehicles and passing vehicles.

Contractor/Consultant
Scarsella Brothers, Inc. of Seattle WA

Recent Progress
This contract was awarded to Scarsella Brothers, Inc. of Seattle, Washington on 8/22/03.  The anticipated cost to construct this project is $3,950,051, which is six percent below the WSDOT engineer’s estimate of $4,192,015.  Scarsella Brothers started work onsite 9/16/03; this quarter they have started clearing the area to be widened (50% Complete).

Design Construction Impacts
There have been three administrative change orders issued this quarter, with no net increase to the project budget.  Because of the area’s climate, construction this year is scheduled to end by mid-November, then resume in the spring as weather allows (estimated April).

Environmental Impacts / Compliance
To comply with project permits, best management practices for construction are being implemented

Impacts to Traffic
Lane closures will occur Monday thru Thursday while Scarsella Bros. is working.  No lane closures are allowed Friday thru Sunday or holidays.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised Jul 03 Jun 03 Completed 4 weeks in advance of schedule.
Contract Awarded Aug 03 Aug 03 Contract rescindment caused two-week delay in award.
Groundbreaking Sep 03 Sep 03 Work started on site 9/16/03.
Open to Traffic Summer 04 No anticipated impacts at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.7 15.3%
Right-of-Way $0.0 0.0%
Construction $4.0 84.7%
Funded Project Costs $4.7 100%

Nickel funds included in above costs

$4.0 84.7%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects