I-90 - Highline Canal to Elk Heights - Complete August 2004

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location

I-90/Highline Canal to Elk Heights –


East of Cle Elum

Project Description
This project constructs a new truck climbing/passing lane on Interstate 90 eastbound from Highline Canal to Elk Heights, to reduce accidents from slower moving vehicles and passing vehicles.

Contractor/Consultant
Contractor Scarsella Brothers, Inc. – Seattle WA

Recent Progress
After the winter shutdown, the contractor, Scarsella Brothers, Inc. of Seattle, Washington, resumed work on the project March 15, 2004.  The first scheduled task is installing temporary traffic control for the remainder of the project.

Design Construction Impacts
Because of the area’s climate, work on the project was suspended November 20, 2003 due to snow and cold temperatures. 

Environmental Impacts / Compliance
To comply with project permits, best management practices for construction are being implemented.

Impacts to Traffic
Lane closures will occur Monday thru Thursday while Scarsella Bros. is working.  No lane closures are allowed Friday thru Sunday or holidays.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised Jul 03 Jun 03 Completed 4 weeks in advance of schedule.
Contract Awarded Aug 03 Aug 03 Contract rescindment caused two-week delay in award.
Groundbreaking Sep 03 Sep 03 Work started on site 9/16/03.
Open to Traffic Summer 04 No impacts anticipated at this time.
   
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.7 15.3%
Right-of-Way $0.0 0.0 %
Construction $4.0 84.7 %
Funded Project Costs $4.7 100 %

Nickel funds included in above costs

$4.0 84.7 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Paul Gonseth, P.E., WSDOT Project Engineer @ (509) 577-1810 Or E-mail: gonsetp@wsdot.wa.gov