Project Title & Location
I-90/Sullivan-State Line Median Barrier & I-90/Sullivan Road to Idaho State Line-Phase 2. Located in the Spokane Valley, MP 292.10 to MP 299.82.
|
Project Description
Installs seven miles of cable median barrier to prevent vehicles from crossing the median and entering into opposing lanes of traffic.
|
|
Contractor/Consultant
Inland Asphalt Co. Spokane WA.
|
|
Recent Progress
Most construction was completed by September 22, 2004, eight months ahead of schedule. Some cleanup and minor adjustments remain which will be completed in the spring of 2004.
|
|
Design Construction Impacts
Because of a conflict with the Argonne Road to Sullivan Road contract a small segment of the cable median barrier was deferred and will be completed by December 2005 with the Argonne Road to Sullivan Road work.
|
|
Environmental Impacts / Compliance
No significant impacts at this time.
|
Impacts to Traffic
No daytime traffic impacts anticipated.
|