Skip Top Navigation

I-90 - Downtown Spokane Viaduct Bridge Deck - Construction Staging

Phase One - Complete


Phase Two - 2007
Phase Two map - shows Westbound lane closure
Click image to enlarge

2007 Construction Season

  1. Westbound I-90 will be rehabilitated and traffic shifted to the east.
  2. Division St. eastbound off ramp may be closed during project if ramp causes traffic delay.
  3. Concrete barrier will be placed to separate opposing traffic.
  4. Speed limits for both directions will be reduced to 45 MPH.
  5. Maple Street eastbound off ramp and westbound on ramp will remain open along with Browne Street eastbound on ramp and Division Street westbound off ramp.

Traffic Configuration
Diagram showing Traffic Configuration - Click image to enlarge
Click image to enlarge