Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley
|
Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.
|
|
Contractor/Consultant
Scarsella Bros., Inc., Seattle WA
|
|
Recent Progress
Reconstruction of the eastbound and westbound lanes is now complete. I-90 from Argonne Road to Sullivan Road is fully open to traffic. All lanes and ramps are open and traffic is operating in its permanent position. Items remaining for spring of 2006 completion include electrical and communication systems and permanent stripping.
|
|
Design Construction Impacts
No issues at this time.
|
|
Environmental Impacts / Compliance
The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.
|
Impacts to Traffic
All lanes and ramps are open and traffic is in its permanent position. Work has been suspended until warmer weather arrives next spring. Drivers should expect some lane closures next spring as the Contractor works to complete the remaining items on this project.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Contract Advertised
|
November 2003
|
May 2003
|
Completed 6 months in advance of schedule. Preexisting funds were used to complete the design and right of way acquisition.
|
|
EB traffic moved to temporary lanes
|
March 2004
|
March 2004
|
All traffic has been moved to temporary lanes. The Contractor completed reconstruction of the eastbound half of the freeway in October 2004..
|
|
EB lanes reconstructed
|
November 2004
|
October 23, 2004
|
EB traffic was moved to its temporary alignment for the winter on October 23, 2004. 1 week ahead of schedule.
|
|
WB traffic moved to temporary lanes
|
March 2005
|
March 12, 2005
|
All traffic has been moved to temporary lanes. Reconstruction of the westbound half of the freeway is in the final stages.
|
|
Open to Traffic
|
Fall 2005
|
November 11, 2005
|
All lanes and ramps are open and traffic is in its permanent position.
|