Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley
|
Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.
|
|
Contractor/Consultant
Scarsella Bros., Inc., Seattle WA
|
|
Recent Progress
Temporary alignment is being constructed in the west bound (WB) lanes with completion expected by November 1, 2003. Drainage installation in the median continues.
|
|
Design Construction Impacts
Scarsella Bros. is required to maintain two lanes of traffic in each direction 6 am to 7 pm weekdays. All ramps must remain open between November 1st and March 1st of each year.
|
|
Environmental Impacts / Compliance
The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.
|
Impacts to Traffic
WB traffic has been moved to it's temporary realigned position. This will allow construction activities, near the median, to continue throughout the winter.
|