Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley
|
Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.
|
|
Contractor/Consultant
Scarsella Bros., Inc., Seattle WA
|
|
Recent Progress
After a winter shutdown, improved weather conditions allowed construction work to re-start on February 23, 2004. Eastbound traffic was moved to temporary lanes on March 13, 2004. Work is now underway on the reconstruction of the eastbound lanes including drainage, noise walls, signing and illumination. Eastbound construction and all ramps will be completed by November 1, 2004.
|
|
Design Construction Impacts
Work is proceeding according to the contract plan.
|
|
Environmental Impacts / Compliance
The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.
|
Impacts to Traffic
All traffic has been moved to its temporary realigned position. This allows construction activities to continue with minimal traffic impact.
|