I-90 - Argonne to Sullivan - Complete June 2006

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley

Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.

Contractor/Consultant
Scarsella Bros., Inc., Seattle WA

Recent Progress

Work has now exceeded the seventy percent complete milestone. Reconstruction of the westbound lanes commenced in March of 2005.  On May 14th paving activities started in these lanes.  Other ongoing activities include the noise wall construction and construction of electrical and communication systems.

Design Construction Impacts

No issues at this time.

Environmental Impacts / Compliance

The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.

Impacts to Traffic

Traffic is now in its temporary realigned position for the 2005 construction season.  Minor ramp reconfigurations will occur early this summer in the WB direction.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised November 2003 May 2003 Completed 6 months in advance of schedule.  Preexisting funds were used to complete the design and right of way acquisition.
EB traffic moved to temporary lanes March 2004 March 2004 All traffic has been moved to temporary lanes.  The Contractor started reconstruction of the eastbound half of the freeway.
EB lanes reconstructed November 2004  October 23, 2004 EB traffic was moved to its temporary alignment for the winter on October 23, 2004.  1 week ahead of schedule.
WB traffic moved to temporary lanes March 2005   March 12, 2005 All traffic has been moved to temporary lanes.  The Contractor has started reconstruction of the westbound half of the freeway.
Open to Traffic Fall 2005   No issues at this time
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 1.6 4.8%
Right-of-Way $ 0.7 2.2%
Construction $ 30 93%
Funded Project Costs $ 32.3 100%

Nickel funds included in above costs

$ 30 93%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Darrel McCallum, WSDOT Project Engineer @ (509) 324-6242 or E-mail: mccald@wsdot.wa.gov