Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley
|
Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.
|
|
Contractor/Consultant
Scarsella Bros., Inc., Seattle WA
|
|
Recent Progress
Work on the eastbound lanes is continuing, including drainage, noise walls, signing and illumination. Placement of Portland Cement Concrete Pavement (PCCP) started in June 2004 near the Pines Road interchange. The eastbound lanes and ramps are on schedule to be completed in November 2004.
|
|
Design Construction Impacts
No issues at this time.
|
|
Environmental Impacts / Compliance
The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.
|
Impacts to Traffic
WB and EB traffic continues in a temporary realigned position. This allows construction activities in the EB lanes to occur with minimal traffic impacts.
|