Project Title & Location
I-90/Argonne Rd. to Sullivan Rd.-Spokane Valley
|
Project Description
This project will add a third lane, in each direction, to Interstate 90 between the Argonne Rd. I/C and the Sullivan Rd. I/C. All existing lanes will be rebuilt with Portland Cement Concrete.
|
|
Contractor/Consultant
Scarsella Bros., Inc., Seattle WA
|
|
Recent Progress
Work has now exceeded the fifty percent complete milestone. Work will continue through the winter on the construction of the noise walls south of I-90 near Argonne Road as weather permits. Eastbound traffic was routed to the new pavement in late October 2004. No additional impacts to traffic are expected until March 2005 when the westbound traffic will be routed onto the temporary configuration during construction of the new lane.
|
|
Design Construction Impacts
No issues at this time.
|
|
Environmental Impacts / Compliance
The Contractor will be using best management practices to mitigate and minimize any potential negative impacts to the environment.
|
Impacts to Traffic
Traffic is now in its temporary realigned position for the winter. No changes/impacts are anticipated over the winter.
|