I-90 - Snoqualmie Pass East - Hyak to Keechelus Dam

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
I-90 - Snoqualmie Pass East - Hyak to Keechelus Dam

Project Description
This project will improve I-90 to provide a safer, more efficient six-lane freeway from Hyak to Keechelus Dam. This project is the first of several projects that will address concerns along I-90 from Hyak to Easton. Tunnels and/or mitigation measures will minimize avalanche closures and hazards due to rockfall. Aging pavement will be replaced to provide a smoother ride. Expanded bridges and culverts will minimize wildlife collisions by providing safer crossings.

Contractor/Consultant
General Engineering Consultant: URS Corporation - Headquartered in San Francisco, CA

Recent Progress
Geotechnical analysis and recommendations from 2007 exploration to be completed this quarter. Road alignment is final. Preliminary design complete and foundation recommendations submitted for Gold Creek & Rocky Run bridges. Preliminary design is in progress for the balance of bridges, walls, snowshed, culverts, drainage systems, stormwater treatment best managment practice, guardrail, signing, lighting and landscaping. Initial design is in progress for off-site stormwater mitigation.

Design Construction Impacts
Road alignments adjusted to minimize cuts into unstable rock at Slide Curve requiring an added retaining wall. Changes to national standards for seismic design critieria resulted in additional analysis and engineering for bridges and walls.  Wall design is now to be based on a 1,000 year seismic event, rather than a 500 year event.

Environmental Impacts / Compliance
SAC concurrence was obtained in Jan. 2008. ESA Biological Assessment was submitted in Jan. 2008. Wetland mitigation is under development, in collaboration with Ecology, Corps of Engineers and other agencies.

Impacts to Traffic
No impacts to traffic this quarter.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Document July 2008 FEIS distribution is scheduled for summer 2008, the ROD is expected in fall 2008. ESA and BO is anticipated by summer of 2008. Design and permitting are on track for a fall 2009 advertisement date.
Right of Way Oct 2009 No impacts anticipated at this time.
Environmental Permits August 2009 If the 5-mile project is broken into phases, permits for the first phase are expected by fall 2009.
Contract Advertised Oct 2009 No impacts anticipated at this time.
Open to Traffic Oct 2014 Changing the Operationally Complete date back to June 2015 was proposed in the Governor's 2008 Supplemental Budget.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $   40.0  7.6 %
Right-of-Way $    5.0  1.0 %
Construction $ 480.0 91.4 %
Funded Project Costs $ 525.0 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 525.0 100 %

  For more information, go to www.wsdot.wa.gov/projects

Graph above includes only PE and RW dollars
Brian White, I-90 Project Director
(509) 577-1874 or whiteb@wsdot.wa.gov

Project Cost Summary and Scheduled Project Milestones reflect the April 2007 Approved Legislative Budget.