I-90 - Eastbound Ramp to SR 202 - Complete October 2007

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
I-90/ EB Ramps to SR-202 - Roundabout

Project Description
This project will provide a two-lane roundabout at the intersection of the eastbound off ramp and on ramp terminals and SR 202.

Contractor/Consultant
Tri-State Construction, INC.

Recent Progress
The Project has started in April 2007. All utility relocation work has been completed.The contractor will be installing high visibility fence to protect sensitive areas as the first order of work. Installation of temporary illumination system, clearing and grubbing and detention pond excavation will begin immediately after, between the months of April and June.

Design Construction Impacts
Daytime lane closures will be required during construction.

Environmental Impacts / Compliance
There is no significant impact identified at this time. The project will construct storm water treatment facility, and temporary erosion controls will be provided during construction to minimize downstream erosion.

Impacts to Traffic
There is single lane closure during daytime and nighttime on SR 202 during construction.

Project Milestones Scheduled Attained Milestone Outlook
Advertisement January 07 January 07
Contract Execution March 8, 07 March 8, 07
Start Construction April 07 April 07
Project Completion October 07 October 07
Open to Traffic October 07 October 07
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.39 21.3%
Right-of-Way $0.00 0.0%
Construction $1.44 78.7%
Funded Project Costs $1.83 100%

Nickel funds included in above costs

$1.44 78.7%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

 Mehrdad Moini, WSDOT Project Engineer @ (206) 440-4312 or E-mail: moinim@wsdot.wa.gov