I-90 - Eastbound Ramp to SR 202 - Complete October 2007

Project Status - Complete
 Project Location Map View entire map



The new design (pdf 1.73 mb) allows drivers entering from E Ribary Way north on SR 202 the flexability to exit the roundabout where they entered from E Ribary Way. Drivers will be able to circle left through the entire roundabout. The old design restricted this movement.

Click to view more photos
View more photos

Overview
We built a two-lane roundabout at the I-90/SR 202 interchange in North Bend. The roundabout will help improve safety and reduce congestion at this busy interchange.

How You Benefit
Cross GlyphImproves Safety
Roundabouts reduce many of the safety hazards of traditional intersections.
Car GlyphRelieves Congestion
Entering vehicles always yield to vehicles within the roundabout. This results in a smooth flow of traffic and eliminates the long lines of vehicles seen at many signals.

Partnerships & Cooperation
We began designing this project in January 2005 and began construction in April 2007. We held an informational open house at the Mount Si Senior Center on Oct. 25, 2005 to answer questions about the proposed roundabout.

At our open house the community said they wanted the option to return to E Ribary Way once they entered the roundabout and we listened. We revisited the proposed teardrop-shaped design and determined that a more traditional roundabout would still fit within the right of way and provide more benefits for drivers in the community.

This project is exempt from the Section 106 process according to provisions of the Programmatic Agreement signed on July 18, 2000 between the Washington State Department of Transportation, the Federal Highway Administration, the State Historic Preservation Officer, and the Advisory Council on Historic Preservation.

Funding

This project was funded through the following sources:

  • 2003 Gas Tax (Nickel Funding)- $1,411,260
  • Existing Funds - $349,843
  • Total Funding from all Sources - $1,761,103

Contact Us
Mike Askarian
WSDOT Project Engineer
6431 Corson Avenue South, NB82-60
Seattle, WA 98108
Phone: (206) 768-5861
E-mail: askarim@wsdot.wa.gov

or

Meghan Soptich
WSDOT Communications
15700 Dayton Avenue North
PO Box 330310
Seattle, WA 98133
Phone: (206) 440-4704
E-mail: sopticm@wsdot.wa.gov

back to top