I-90 - Replaces Potato Hill Bridge - Complete December 2006

Quarterly Project Report Update for Quarter Ending September 2005

Project Title & Location
I-90/Moses Lake Area-Bridge Clearance – Moses Lake

Project Description
Acquire right of way and replace the low clearance Potato Hill Bridge to eliminate a detour now required for legal-height trucks, and reduce the risk of over-height trucks hitting the bridge on Interstate 90. Design is funded from current revenue sources. Right of way and construction are funded from these new revenues.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The project remains on schedule and within budget.  The 2005 Washington State Legislature appropriated $750,000 to construct a pedestrian bridge adjacent to the new bridge.  The WSDOT has determined that it is less expensive to construct one wider bridge rather than constructing two separate bridges.  This new bridge will accommodate vehicles, pedestrians and bicycles.  The combined structure will also give Grant County and the City of Moses Lake the option of converting the bridge to a four lane structure as traffic volumes increase and still provide pedestrian and bicycle access.   The project will impact 3 parcels.  Right of way funding has been approved, appraisals complete, and offers being made.  Coordination with the City of Moses Lake concerning bridge lane configuration continues.

Design Construction Impacts
The project will require the relocation of several utilities in the area including Grant County PUD, Quest, a private irrigation line and a City of Moses Lake sewer main.  The utilities were formally notified in September 2002 about the project.  Relocation of affected utilities will occur during the spring and summer of 2005.  Coordination with the City of Moses Lake will be ongoing during the Construction phase.

Environmental Impacts / Compliance
Biological Assessment was completed in May 2001.  Environmental Classification Summary signed May 2001.  SEPA, Determination on Non-Significance checklist signed May 1995.

Impacts to Traffic
Traffic on I-90 will experience temporary lane closures during bridge construction.  Traffic on Potato Hill Rd. will be allowed to travel over the existing bridge during the construction of the new bridge and will be directed under temporary traffic control while tie ins are made to the new alignment when the new bridge is ready.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised December 2005 Redesigning structure to incorporate the additional width for pedestrians and bicycles.
Contract Awarded January 2006 No issues at this time.
Groundbreaking Spring 2006 No issues at this time.
Open to Traffic Fall 2006 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.32 m 8.3 %
Right-of-Way $0.34 m 8.8 %
Construction $3.20 m 82.9 %
Funded Project Costs $3.86 m 100 %

Nickel funds included in above costs

$3.58 m 92.7 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Joel Voth, WSDOT Project Engineer @ (509) 667-2870 or E-mail: VothJ@wsdot.wa.gov