|
Project Title & Location
I-90/Moses Lake Area-Bridge Clearance – Moses Lake
|
Project Description
Acquire right of way and replace the low clearance Potato Hill Bridge to eliminate a detour now required for legal-height trucks, and reduce the risk of over-height trucks hitting the bridge on Interstate 90. Design is funded from current revenue sources. Right of way and construction are funded from these new revenues.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
Design has been completed and has been on the shelf since October 2002. The design will impact 3 parcels. Right of way funding has been approved and the appraisal process has begun. Coordination with the City of Moses Lake concerning utility crossings and a proposed pedestrian crossing continues.
|
|
Design Construction Impacts
The project will require the relocation of several utilities in the area including Grant County PUD, Quest, a private irrigation line and a City of Moses Lake sewer main. The utilities were formally notified in September 2002 about the project. Relocation of affected utilities will occur during the spring and summer of 2004. Coordination with the city of Moses Lake will be ongoing during the Construction phase.
|
|
Environmental Impacts / Compliance
Biological Assessment was completed in May 2001. Environmental Classification Summary signed May 2001. SEPA, Determination on Non-Significance checklist signed May 1995.
|
Impacts to Traffic
Traffic on I-90 will experience temporary lane closures during bridge construction. Traffic on Potato Hill Rd. will be allowed to travel over the existing bridge during the construction of the new bridge and will be directed under temporary traffic control while tie ins are made to the new alignment when the new bridge is ready.
|