I-90 - West of George - Paving - Complete May 2014

Project Status - Complete
Click to enlarge
View entire map
This project replaced the asphalt driving lanes on I-90 from the Vantage Bridge (MP 137.67) to the Beverly-Burke Overpass (MP 148.45)

Click to enlarge
View entire photo - Before -Shoulder cracking on I-90.

Click to enlarge
View entire photo
- Before - A pothole forming at the end of this crack.

Overview

This P-1, Roadway Preservation project replaced the asphalt driving lanes on I-90 for 11 miles from the Vantage Bridge to a mile west of George. The asphalt was also replaced at the Silica Road Interchange (Exit 143), the Wanapum Scenic View Area (Exit 139 Eastbound), and Echo Scenic View Area (Exit 139 Westbound). Four miles of badly deteriorated asphalt shoulders were replaced just west of George. This project included fog sealing of the driving lanes for the SR 26 interchange (Exit 137) at the east end of the Vantage Bridge.

The eastbound left lane and both westbound lanes showed signs of distress. Cracks and potholes were forming in the
driving lanes and some of the shoulders. 

Construction started Mar. 21 and was complete May 30.

 

How You Benefit
Cross GlyphImproves Safety
A Smoother driving surface

Partnerships & Cooperation
Work plans were scheduled to reduce impacts to communities and businesses in the corridor such as concerts at the Gorge.

Funding

Financial Data for PIN 200000G, 209000I
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,714
CWA $0
Total $4,714
The project was advertised for private contractor bids Dec. 9, 2013. Three qualified bids were opened Jan. 16. On Jan. 21 Contract #8568 was awarded to Central Washington Asphalt Inc. for $2,872,536.80, 13% under the engineering estimate