I-90 - George East – Paving – Complete August 2005

Project Status - Complete
This project is located in Grant County on I-90, the SR 281(Quincy/George)Interchange, to the west end of Dodson Road Interchange.  View entire map  This project is located in Grant County on I-90, from milepost 148.44, the SR 281(Quincy/George)Interchange, to milepost 164.24, the west end of Dodson Road Interchange.

This earthen berm at Adams Road will be replaced with a shock absorbing structure that means current Federal Highway Administration standards.
View entire photo
This earthen berm was replaced with a shock absorbing structure.


View entire photo
A turnaround for emergency vehicles was constructed at MP 155.

A new right turn island will be constructed at the Quincy/George exit where SR 281 and SR 283 intersect at Murphy's Corner.
View entire photo
  A new right turn island was constructed at the Quincy/George exit.


The exit from the eastbound Winchester Safety Rest Area will be widened.
View entire photo
The exit at the eastbound Winchester Safety Rest Area was widened.
 
The truck exit lane from the westbound Winchester Safety Rest Area will be widened, too.
View entire photo
  The truck exit lane from the westbound Winchester Safety Rest Area was widened, too.

Overview
This Preservation Project paved 16 miles of Interstate 90 between George and Moses Lake to preserve the existing pavement structures, extend pavement service life, and improve safety by updating features including guardrail, striping and installation of new cable barrier in the median. It required grinding the driving lanes to remove ruts and overlaying the east and west bound lanes on I-90 with Hot Mix Asphalt. The project also paved the ramps and bridges at the Adams Road and SR 281 Interchanges and included improvements at the Winchester Wasteway Safety Rest Areas.

How You Benefit
Cross GlyphImproves Safety
Highway safety feature updates included new guardrail, rumble strips and cable barrier in the median to prevent head on collisions.

Partnerships & Cooperation
Construction began April 11,  2005 and was completed August 25th. 125 working days were scheduled, but the project was completed in 91 days. To avoid traffic restrictions over the busy 4th of July weekend, the paving was scheduled to be completed by July 1st. The median cable barrier installation was incorporated into the paver, saving time and money.  That phase was complete, July 22nd.  Rumble strip installation, striping, signage and final clean up work was complete August 25th, 2005.

Funding
Bids were opened on January 6th, 2005 and Central Washington Asphalt, Inc. was the successful bidder among five contractors. Contract #C6881 was awarded January 10th for $3,847,155.69, 1% below the engineering estimate.

This project was funded through the following sources:

· Pre-Existing Gas Tax - $4.4 million

· Total funding from all sources - $4.4 million

This project was completed $317,095 under budget.

Contact Us
Project Engineer Bob Romine
WSDOT North Central Region Project Office
PO Box 98
Wenatchee, WA 98807
Phone: 509-667-2880 or toll-free 1-800-461-8816.