Overview
We replaced 13 freeway exit signs on westbound I-90 in the Eastgate area of Bellevue to improve sign clarity, helping unfamiliar drivers reach their destination more easily.
The signs on westbound I-90 in this area were very old and had lost reflectivity. By replacing the signs and revising the layout and messaging, we were able to improve communication to drivers and comply with current federal guidelines.
Project timeline
- January 2011: Complete sign designs
- March 2011: Begin construction
- July 2011: Complete construction
 | Improves Safety
This project improves safety by reducing unnecessary or last minute lane changes caused by driver confusion.
|
Partnerships & Cooperation
WSDOT worked with the city of Bellevue to communicate to the communities impacted during construction.
Funding
This project is funded through our low-cost enhancement project fund.
Total project cost: $80,000