I-90 - Increase Vertical Clearance on Cle Elum River Bridge - Complete Novermber 2004

Quarterly Project Report Update for Quarter Ending December 2004

Project Title & Location
I-90/ Cle Elum River Br. 90/134N -
West of Cle Elum

Project Description
This project will provide increased vertical clearance for the westbound Cle Elum River bridge (90/134N).

Contractor/Consultant
Diamaco Inc. - Bellevue WA

Recent Progress

Bridge steel modification complete and open to trafffic on November 4, 2004.  All work on the project completed by November 19, 2004.

Design Construction Impacts

Project complete November 19, 2004.

Environmental Impacts / Compliance
All environmental documents were completed in the fall of 2003.  All work occurred within the existing right of way.  Impacts were minimal and no mitigation was required for this project.  Best management practices were used during construction.

Impacts to Traffic

Project complete November 19, 2004.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Document Oct. 2003 Oct. 2003 Completed on schedule.
Contract Advertised March 2004  March 2004 Completed on schedule
Contract Awarded April 2004 April 2004 Completed on schedule.
Groundbreaking May 2004 July 2004

Ground breaking was delayed due to steel unavailability.

Open to Traffic Summer  2004 November 2004 Delayed due to steel procurement issues.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.1 12.5%
Right-of-Way $0.0 0.0%
Construction $0.7 87.5%
Funded Project Costs $0.8  100%

Nickel funds included in above costs

$0.8 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Paul Gonseth, P.E., WSDOT Project Engineer @ (509) 577-1810 Or E-mail: gonsetp@wsdot.wa.gov