|
Project Title & Location
I-90/ Cle Elum River Br. 90/134N - West of Cle Elum
|
Project Description
This project will provide increased vertical clearance for the westbound Cle Elum River bridge (90/134N).
|
|
Contractor/Consultant
Diamaco Inc. - Bellevue WA
|
|
Recent Progress
Bridge steel modification complete and open to trafffic on November 4, 2004. All work on the project completed by November 19, 2004.
|
|
Design Construction Impacts
Project complete November 19, 2004.
|
|
Environmental Impacts / Compliance
All environmental documents were completed in the fall of 2003. All work occurred within the existing right of way. Impacts were minimal and no mitigation was required for this project. Best management practices were used during construction.
|
Impacts to Traffic
Project complete November 19, 2004.
|