I-82 - Valley Mall Blvd Interchange - Rebuild Interchange

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
I-82 - Valley Mall Boulevard Interchange - Rebuild Interchange

Project Description
This project improves connections to the interstate and encourages economic growth and development for both Union Gap and Yakima. The interchange reconfiguration will provide increased motorist safety, additional capacity, and help free up movement on and off the interstate to connect smoothly with the expanding local road system.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
A surveying consultant is currently surveying the project to show the anticipated right-of-way impacts the project will require.
Access plans are currently being worked on to prepare for the design/access hearing, which is scheduled for late winter/ early spring of 2008.
Individual meetings are being scheduled to update adjacent property owners on the project.

Design Construction Impacts
Early comments from resource agencies center on impacting the floodplain and fully allowing possible future flood waters to flow through the new interchange. This risk cannot be quantified until the discipline reports and consultations with resource agencies are complete.
To improve Level of Service (LOS) a loop ramp for the westbound on-ramp was added to the roundabout alternative. This addition required the design team to evaluate the replacement of the I-82 mainline bridges for vertical clearance. Preliminary results of this evaluation show the need to adjust the I-82 profile. Although these additions will increase the cost of the roundabout alternative the total project cost is within budget at this time.

Environmental Impacts / Compliance
The environmental process is just beginning. Wetland impacts are possible.  Design alternatives related to Spring Creek have been discussed with fisheries resource agencies.

Impacts to Traffic
Occasional one lane closures and minor detours are anticipated.

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start June 04 June 04 Preliminary engineering has started. The current design concept is the three roundabouts with a single loop ramp.
Environmental Document Complete Oct 08 Design alternative discussions have been on going with fisheries resource agency. NEPA discipline report site investigation has begun.
Right of Way Certified Oct 09 No impacts anticipated at this time.
Contract Ad Date Oct 09 No impacts anticipated at this time.
Operationally Complete Oct 11 No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 3.0  9.2 %
Right-of-Way $ 5.7 17.6 %
Construction $ 23.7 73.2 %
Funded Project Costs $ 32.4 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 29.7 91.7 %

  For more information, go to www.wsdot.wa.gov/projects

Graph includes $275K spent prior to January 2006
Jeff Minnick, WSDOT Project Engineer

(509) 577-1703 or MinnicJ@wsdot.wa.gov
Project Cost Summary and Scheduled Project Milestones reflect the April 2007 Approved Legislative Budget.