I-5 - SR 161/SR 18 Triangle Improvements

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
I-5/SR 161 I/C & SR 18 I/C (Triangle)

Project Description
The I-5/SR 161/SR 18 Interchange Improvement project (Triangle Project Phase 1) includes replacing a cloverleaf loop ramp with a flyover ramp for WB SR 18 to SB I-5 traffic and provide a new WB SR 18 connection to SR 161. The I-5/SR 18 cloverleaf interchange is defined as a High Accident Location. Eliminating one of the loop ramps will eliminate the weave on WB SR 18 and SB I-5. These improvements will improve traffic flow and safety.

Contractor/Consultant
Consultant Berger/Abam

Recent Progress

Held VE workshop September 25-28, 2006.  VE team developed 6 proposals which we are evaluating at this current time.

Started purchasing property needed for S 356th ramp.

Updated program management on project ageing projections and working with CVEP consultant to update project cost estimate.

Have obtained the right-of-entry permit and are scheduled for ground water piezometers installation the second week of November.

Coordinating with WSDOT environmental to determine how project will address fish passage issues.

Updated project Web page.

Design Construction Impacts
Need to secure key right of way for new offramp to S. 356th Street.  We are nearing completion of one parcel with the second parcel sill in negotiations; we anticipate completion of early acquisition buy summer 2007.

Environmental Impacts / Compliance
Environmental impacts identified by preliminary discipline reports are minimal.  We have decided to switch the NEPA classification from an Environmental Assessment (EA) to a Documented Categorical Exclusions (DCE)

Impacts to Traffic

The consultant will develop a staging plan to minimize traffic impacts during construction.  We also plan on organizing a Value Engineering (VE) study to examine ways to reduce traffic impacts during construction.

Project Milestones Scheduled Attained Milestone Outlook
Selection of preferred alternative Feb 05 Feb 05
Project Open House April 07 If NEPA classification is switched to a DCE we could hold a public open house in early 2007.
IJR Feb 07  
Advance R/W acquisition Jan 06

 

   
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $22.7m 20.3%
Right-of-Way $8.0m 7.1%
Construction $81.3m 72.6%
Funded Project Costs $112.0m 100.0%

Nickel funds included in above costs

$3.0m 2.7%

2005 Transportation Partnership Account

$100.0m 90.7%

  For more information, go to www.wsdot.wa.gov/projects

Bruce Nebbitt, WSDOT Project Engineer @ (206) 464-1363 or E-mail: NebbiEB@wsdot.wa.gov