Recent Progress
Held VE workshop September 25-28, 2006. VE team developed 6 proposals which we are evaluating at this current time.
Started purchasing property needed for S 356th ramp.
Updated program management on project ageing projections and working with CVEP consultant to update project cost estimate.
Have obtained the right-of-entry permit and are scheduled for ground water piezometers installation the second week of November.
Coordinating with WSDOT environmental to determine how project will address fish passage issues.
Updated project Web page.
|