I-5 - Southbound Ramps at SR 11, Old Fairhaven Parkway - Complete May 2007

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
 

Interstate 5 - Southbound Ramps at State Route 11 - Old Fairhaven Parkway

Located at the interchange of Interstate 5 and Old Fairhaven Parkway in Bellingham.

Project Description
The intersection of the southbound ramps from I-5 with Fairhaven Parkway in Bellingham is experiencing increased congestion. This project will improve safety by reducing traffic conflicts that are occurring at this intersection. The traffic problems will be improved by adding a signal for the southbound ramps, installing another turn lane on the southbound off ramp, and modifying the 32nd Street access connection with Fairhaven Parkway.

Contractor/Consultant
The construction project was awarded to Wilder Construction Company on March 27, 2006 for $1,319,5000 dollars.

Recent Progress
The City of Bellingham contract work 99% completed, including installing a large detention vault under 30th St, reconstructing Donovan and 30th St., sidewalks ,and illumination bases. Luminaire poles on Donovan can be installed now that the utility relocation have been completed.  The illumination system on Donovan is scheduled to be tuned on by the end of April 07.  WSDOT contract work was completed December 06 with the turning on of the new signal at I-5 and Fairhaven.

Design Construction Impacts
Access to and from Fairhaven from 32nd street  will be permanently closed starting July 27.  Donovan and 30th street were reconstructed to mitigate for the closure of 32nd street.

Environmental Impacts / Compliance
There will be adherence to permit requirements.

Impacts to Traffic
Expect up to 15 minute traffic blockage for luminaire erection on 30th street for the third week of April. 

Project Milestones Scheduled Attained Milestone Outlook
Contract Award March 2006 March 06 Milestone achieved March 27,2006
Start Construction May 2006 May 06 Contractor scheduled to start work after detention vault is manufactured.
Closing 32 and Street  access June 2006 July 06 Permanent closing of the 32nd Street access connection with Fairhaven Parkway in late May or early June.
Project opened to traffic.  February 2007 December 06 The I-5 southbound ramp at Fairhaven parkway will have been widened new signal installed and the improvements to Bellingham streets completed. Planned open to traffic is December 2006
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.46 m 27.9%
Right-of-Way $0.00 m 0.0%
Construction $1.19 m 72.1%
Funded Project Costs $1.65 m 100.0%

Nickel funds included in above costs

$1.00 m 60.6%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

David Crisman, WSDOT Project Engineer @ (360)428-1593 or E-mail: crismad@wsdot.wa.gov

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget