WSDOT Projects

text size: T T T

I-5 Noise Wall Project: Construction Photo Essay

  

The I-5 North and Harvard Ave E signs show the edge of the Stage 1 project area. Stage 1 Photos
Preparing the Site
Noise Wall Fabrication
Finished Noise Wall Sections
Installed Noise Walls Along Harvard Avenue
Completed Harvard Avenue Noise Walls

Stage 1 Completion and Stage 2 Groundbreaking
Event Images

Stage 2 Photos
Boylston Avenue Architectural Treatments
Construction Progress
Completed Boylston Avenue Wall


Stage 1: Harvard Avenue Developments

  
Preparing the Site

The first stage of the two stage I-5 Roanoke Vicinity Noise Wall Project is lengthy and complex.  Although there has been minimal construction activity along Harvard Avenue East, the project is progressing.  Crews have been preparing the site for the upcoming wall installation.

Crews drill shafts for noise panels along Harvard Avenue
View enlarged image
Close-up image of a finished shaft.
View enlarged image
After clearing and grubbing the soil, crews began drilling shafts into the ground for the noise wall supports and foundations. Each hole is 30 inches in diameter and 13 feet deep.  After all of the shafts are drilled, construction crews will line each shaft with a sheet of steel to reinforce the hole and provide support for the panel anchors.

Two anchor bolts await positioning in noise wall shafts
View enlarged image

Worker prepares each shaft with steel lining and anchor bolts.
View enlarged image
The image above shows two anchor bolts laying side by side before they are positioned in the shaft.  The curved ends are where the noise panels will be attached to each bolt. Once the shafts are drilled and lined, crews place anchor bolts vertically into the holes. After the anchor bolts are inserted, cement is poured over the bolts to form the structural support for the noise panels.

Example of a completed foundation shaft after cement has been poured and set.
View enlarged image

This last image shows a completed shaft after the cement was poured over the anchor bolt and the base has cured.  Once all the shafts are formed, noise panels will be attached.   

top

  
Noise Wall Fabrication

Meanwhile, in Puyallup, crews were fabricating the noise walls in preparation for installation.


The rebar skeleton of a noise wall.
View enlarged image

Rebar skeleton before cement is poured over it.
View enlarged image

The rebar skeleton of a noise wall.

The rebar is then placed in a mold for the noise wall and cement is poured over it.

Here crew members take final measurements and position the rebar within the noise wall mold.
View enlarged image

After the cement is poured, this machine will apply texture to the noise walls for added noise diffraction.
View enlarged image

Here crew members take final measurements and position the rebar within the noise wall mold.


 

After the cement is poured, this machine will apply texture to the walls for added noise diffraction.
Crews carefully add texture to a recently poured noise wall. The walls with smoother textures will face Harvard and Bolyston Avenues, while the opposite sides that will face I-5 will have more rough striations.
View enlarged image
Crews carefully add texture to a recently poured noise wall. The walls with smoother textures will face Harvard and Bolyston Avenues, while the opposite sides that will face I-5 will have more rough striations.

top

  
Finished Noise Walls

Below are images of recently completed noise walls.  After they have cured they will be taken to Harvard Avenue and attached to the anchor bolts. 

A finished Harvard Avenue noise wall panel curing in the sun.
View enlarged image

                  

Each ridge on the Harvard side of the noise walls is approximately one inch wide.  These ridges help further mitigate noise pollution from nearby traffic.
View enlarged image
A finished Harvard Avenue noise wall panel curing in the sun.

Each ridge on the Harvard side of the noise walls is approximately one inch wide.  These ridges help further mitigate noise pollution from nearby traffic.

A finished noise wall - the side shown will face I-5.
View enlarged image

The ruler lends perspective to the size of the grating
View enlarged image
A finished noise wall - the side shown will face I-5. The ruler lends perspective to the size of the grating.

top


Installed Noise Walls Along Harvard Avenue

These recent images show installed noise walls along Harvard Avenue. 


The view along Harvard Avenue facing south.
View enlarged image


The view of the Harvard Avenue noise walls facing south.


The view of the installed noise walls, looking west from the North Capitol Hill neighborhood.
View enlarged image


A view of installed noise walls, looking west from the North Capitol Hill neighborhood.

The view down Harvard Avenue East with the installed noise walls.
View enlarged image

Installed noise walls along Harvard Avenue East with view of downtown Seattle.

The view along Harvard Avenue East facing north.
View enlarged image

Noise walls along Harvard Avenue Easat facing north.


Crew members put finishing touches on the installed noise walls along Harvard Avenue East.
View enlarged image

Crew members put finishing touches on installed noise walls along Harvard Avenue East.

A Mowat crew member uses a drill to smooth the texture of the installed noise walls.
View enlarged image

A Mowat crew member uses a drill to smooth the texture of the installed noise walls.

Triangular architectural treatments at the base of the Harvard Avenue East nosie walls.
View enlarged image

Triangular architectural treatments at the base of the Harvard Avenue East noise walls.

A close-up of the architectural treatments at the base of the Harvard Avenue East noise walls.
View enlarged image

A close-up of the architectural treatments at the base of Harvard Avenue East noise walls.

A Mowat team member inspects a noise wall on the trailor before it is installed.
View enlarged image

A Mowat team member inspects a noise wall panel before it is installed.

A crane lifts a noise wall and positions it for installation.
View enlarged image

A crane lifts a noise wall and positions it for installation.

 

top

Completed Harvard Avenue Noise Walls


The view of the completed Harvard Avenue noise walls looking west from the Roanoke Park and Portage Bay neighborhoods.
View enlarged image

A view of the completed Harvard
Avenue noise walls looking west
from the Roanoke Park and Portage
Bay neighborhoods.



The completed Harvard Avenue noise walls facing South with a view of Seattle
View enlarged image

The completed Harvard Avenue
walls facing south with a view of Seattle.





An angled view of the Harvard Avenue noise walls looking north
View enlarged image

An angled view of the Harvard
Avenue nosie walls looking north.

A view of the Harvard Avenue architectural treatments.
View enlarged image

A view of the Harvard Avenue architectural treatments looking south.

A close-up of the Harvard Avenue architectural treatment
View enlarged image

A close-up of the Harvard Avenue architectural treatments.

The completed Harvard Avenue noise walls
View enlarged image

The completed Harvard Avenue
noise walls.


top

Stage 1 Completion and Stage 2 Groundbreaking Celebration

Community Representative Colleen McGrath helps celebrate the completion of the Harvard avenue noise walls
View enlarged image

Community representative Colleen McGrath helps celebrate the completion of the Harvard avenue noise walls.

Members of the Roanoke Vicinity Noise Wall Project join Secretary of Transportation Doug MacDonald in front of the Stage 2 Nickel sign
View enlarged image

The Roanoke Vicinity Noise Wall Project Team and Secretary of Transportation Doug MacDonald stand with the Stage 2 Nickel sign.


Speaker of the House Frank Chopp, community representative Colleed McGrath and Representative Ed Murray stand with the new NIckel sign for the Boylston avenue noise walls
View enlarged image

Speaker of the House Frank Chopp, community representative Colleen McGrath, and Representative Ed Murray stand with the Nickel sign for the future Boylston avenue noise walls.

The construction team stands with the new Nickel sign after the unveiling
View enlarged image

The noise wall construction team pose with the new Nickel sign after the unveiling ceremony.



Community members talk with the noise wall project team after the event
View enlarged image

Community members mingle with the Roanoke Vicinity Noise Wall Project Team after the Stage 2 unveling and celebration.




Secretary of Transportation Doug MacDonald and Project Director Maureen Sullivan talk with a community member directly following the Noise Wall Event
View enlarged image

Secretary of Transportation Doug MacDonald and Project Director Maureen Sullivan talk with a community member following the unveiling.


Stage 2: Boylston Avenue Developments


Architectural Treatments

Below are recent images of the architectural treatments that will adorn the noise walls after they have been installed. Local artists and the surrounding communities designed these.

12 foot section of the architectural treatment
View enlarged image

Close up of the architectural treatment
View enlarged image

This panel will be installed onto the noise walls along the Bolyston Avenue side of the project. This panel is 12 feet long by 3 feet wide. This is one of two designs that will be used for this project.

The panel above is a close-up of the architectural treatment to the left.
Close-up of a butterfly on the architectural treatments
View enlarged image

Side view of an architectural treatment that will run along Boylston Avenue
View enlarged image
A butterfly design that will appear on the Bolyston side of the noise wall. Here is a side view of one of the architectural treatments that will run along Boylston Avenue.

top

   
Construction Progress

Recent construction photos from along Boylston Avenue. 

A north facing view of the construction along Boylston Avenue.
Click to view enlarged image

A north facing view of the construction along Boylston Avenue.



Construction progress looking north along I-5 and Boylston Avenue east.
Click to view enlarged image

Construction progress looking north along I-5 and Boylston Avenue east


Construction crews working along Boylston Avenue.
Click to view enlarged image

A south facing view of construction along Boylston Avenue east.

Crews begin drilling shafts for noise wall supports.
Click to view enlarged image

Crews begin drilling shafts for noise wall supports along Boylston Avenue.



   
Completed Boylston Avenue Wall

Completed noise wall along Boylston Avenue
Click to view enlarged image
Completed noise wall along
Boylston Avenue.

top