Recent Progress
In April, the legislature transferred $15 Million in Nickel funds to this project bringing the total to $55 million of Nickel funds. Clark County has secured $8 million in TIB funds, $11 million in Fed. Earmarks, and $6 million from the County Road Fund, bringing the total funding to $80 million. Clark County will be pursuing the additional $14 million needed to complete the project and will be talking with county commisioners and legislators for approval to advance funding for construction in 2008.
In April, Consultant HDR received the notice to proceed with the environmental assessment that is currently underway and is scheduled to be complete in Spring 2006.
A VE study and 30% plans review were conducted in September 2005. The project is on schedule for a proposed construction start date of Spring 2008, provided advanced funding can be secured by the County.
|