I-5 - Reconstruct Interchange at NE 134th

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location
Reconstruct I-5 Interchange at NE 134th Street

Project Description
Reconstructs the NE 134th Street interchange at the junction of I-5 and I-205. The improvement is needed to maintain safety on I-5 and I-205 and to keep traffic moving at acceptable levels through the interchange area. It includes construction of a supplemental interchange and I-5 crossing at NE 139th Street.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress
This project is currently in the early design phase.  Preliminary staging and alignment alternates are being investigated at this time.  In November 2002, the Federal Highway Administration (FHWA) granted approval for modifying the accesses on I-5 and I-205 at NE 134th Street.  In April 2003, FHWA approved a modified interchange concept for this location.  WSDOT received a $40 million funding package from the Washington State Legislature in 2003 for this project.  With this funding, the environmental process and project design can begin, with construction proposed to start in 2011.

Design Construction Impacts
It is too early in the project to determine the magnitude of these impacts.

Environmental Impacts / Compliance

The necessary environmental impact study for this project will detail the project's direct and indirect environmental impacts (natural, ecological, societal and economic) in order to guide final design and construction.  This project may provide an opportunity to improve wetland habitat and storm water runoff in the project area.

Impacts to Traffic
There will be significant impacts to traffic which will be determined as the project develops.

Project Milestones Scheduled Attained Milestone Outlook
Design Start August 2003 August 2003 Preliminary staging and alignment alternates are currently under investigation.
Record of Decision June 2009 No issues at this time
Right of Way Complete March 2011 No issues at this time
Ad Date March 2011 No issues at this time
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 3 7.5
Right-of-Way 5 12.8
Construction 32 80
Funded Project Costs 40 100

Nickel funds included in above costs

40 100

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Don Owings, WSDOT Area Engineer @ (360) 905-1500 Or Email: swi-5widening@wsdot.wa.gov