Recent Progress
Project design is progressing towards 90% completion anticipated for September 2008.
NMFS did not concur with informal consultation for the Biological Assessment (BA) and has requested the project enter in to formal consultation. NMFS has indicated that their Biological Opinion will be completed by the end of July 2008. The Environmental Assessment is nearly complete and is awaiting the completion of the BA.
Construction may begin in 2010 if environmental documentation is complete, right of way acquired, permits are acquired, design is finalized, and Clark County has completed the financing plan.
|