Recent Progress
Project design is progressing towards 90% completion anticipated for March 2009.
NMFS is expected to provide the Biological Opinion on the Biological Assessment in December 2008. The Final Draft of the Environmental Assessment is complete and is awaiting the completion of the BA.
Appraisals have been completed on several parcels and negotiations are underway. The final acquisition process will begin when NEPA is complete.
Construction may begin in 2010 if environmental documentation is complete, right of way acquired, permits are acquired, design is finalized, and Clark County has completed the financing plan.
|