I-5 - Reconstruct Interchange at NE 134th

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
Reconstruct I-5 Interchange at NE 134th Street and NE 139th Street

Project Description
Reconstructs the NE 134th Street interchange at the junction of I-5 and I-205. The improvement is needed to maintain safety on I-5 and I-205 and to keep traffic moving at acceptable levels through the interchange area. It includes construction of a supplemental interchange and I-5 crossing at NE 139th Street.

Contractor/Consultant
Environmental Assessment Consultant: : Parsons Brinkerhoff.  This is a partnership project with Clark County.

Recent Progress
Design is progressing towards 90%.  A geotechnical exploration is underway and is expected to be completed by the end of the year.  A Value Engineering study was held in September to develop solutions for stormwater treatment.  The Environmental Assessment is nearly complete and is awaiting the completion of the Biological Assessment which is in formal consultation with NMFS.

Construction of stage one will begin in 2010 if environmental documentation is complete, permits are acquired, design is finalized, and Clark County has completed the financing plan.

Design Construction Impacts
The project team is determining the optimal project phasing plan to fit the project financial plan. Coordination with utility companies is underway.  An existing Park and Ride lot will be relocated and improvements to several local streets will be made. 

Environmental Impacts / Compliance
 The Environmental Assessment for this project will detail the project's direct and indirect environmental impacts (natural, ecological, societal and economic) in order to guide final design and construction.  This project may provide an opportunity to improve wetland habitat and storm water runoff in the project area.  The Biological Assessment has been determined to need a formal consultation by NMFS.

The EA is progressing toward a final draft.  It is anticipated to be complete in 2008.

Impacts to Traffic
There will be impacts to traffic during construction, which will be determined as the project develops.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering October 2003 October 2003 Began on time.
Environmental Documentation Complete August 2010 On schedule.
Right of Way Complete March 2011 No issues at this time - on schedule.
Ad Date April 2011 No issues at this time - on schedule.
Operationally Complete June 2013
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.3 4%
Right-of-Way $7.0 9%
Construction $71.5 87%
Funded Project Costs $81.8 100%

Nickel funds included in above costs

$81.8 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

 Casey B. Liles, WSDOT Area Engineer, (360) 905-1500 or e-mail:  swVanc@wsdot.wa.gov