I-5 - Reconstruct Interchange at NE 134th

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
Reconstruct I-5 Interchange at NE 134th Street and NE 139th Street

Project Description
Reconstructs the NE 134th Street interchange at the junction of I-5 and I-205. The improvement is needed to maintain safety on I-5 and I-205 and to keep traffic moving at acceptable levels through the interchange area. It includes construction of a supplemental interchange and I-5 crossing at NE 139th Street.

Contractor/Consultant
Environmental Assessment Consultant: HDR

Recent Progress

The project has been broken into two stages. Stage one will include the work related to the interstate system.  Stage 2 will make improvements at NE 134th Street and possibly widen I-5 between 134th Street and I-205.  This proposal is included in the 2007-2009 budget request.

 

Construction of phase one will begin in 2009 if permits are acquired, design is finalized, and the county has completed the financing plan.  Updated County Comprehensive Plan traffic numbers required the relocation of the SB off-ramp to the NE 139th Street Interchange.  An additonal auxillary lane is being designed on SB I-5 north of NE 139th St.  A loop ramp from NE 20th Avenue to SB I-205 is added.

 

Design Construction Impacts
It is too early in the project to determine the magnitude of these impacts.  Mitigation for the budget and scope issues may require some redesign.

Environmental Impacts / Compliance

The Environmental Assessment and impact study for this project will detail the project's direct and indirect environmental impacts (natural, ecological, societal and economic) in order to guide final design and construction.  This project may provide an opportunity to improve wetland habitat and storm water runoff in the project area.

The EA is on schedule and the draft discipline reports are currently under review.

Impacts to Traffic
There will be impacts to traffic during construction, which will be determined as the project develops.

Project Milestones Scheduled Attained Milestone Outlook
Design Start August 2003 August 2003 Began on time.
NEPA Completion December 2009 No issues at this time - on schedule.
Right of Way Complete March 2011 No issues at this time - on schedule.
Ad Date March 2011 No issues at this time - on schedule.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.0 5%
Right-of-Way $5.0 9%
Construction $47.0 86%
Funded Project Costs $55.0 100%

Nickel funds included in above costs

$55.0 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Project costs do not reflect The Governor's 2007-09 Proposed Budget.

Casey B. Liles, WSDOT Area Engineer, (360) 905-1500 or e-mail:  mailto:i5NE134th@wsdot.wa.gov?subject=I-5 Vancouver - NE 134th Street Interchange Project