|
Recent Progress
A Value Engineering Study was recently completed on the project that produced three recommendations that the team is now reviewing and validating. They will make a decision on implementation of the recommendations on December 8th with the Oversight Committee.
HDR has submitted the draft environmental discipline reports which have now been reviewed. The draft Biological Assessment will be submitted in December 2005 pending the decision to implement the VE recommendations. PB is working on revising the Access Point Decision Report which will also be submitted in December for review.
A preliminary geotechnical report was released that revealed a high groundwater table. This led to the current hydrogeological investigation that is being conducted by Landau. This study will give the project team the information needed to decide on whether or not to implement the VE recommendations.
The project team is still looking at innovative ways for the construction and completion of this project to meet the target dates set by the county, who is Project Manager. The County's target date for project completion is the end of 2010.
WSDOT and Clark County are working on an agreement that will transfer the $55 Million in Nickel funds to the project fund in which the county will be responsible for obtaining the rest of the funds for the project. These funds may be used to start purchasing R/W and early construction.
|