Ramp closure schedule and detours

Detours will direct drivers around expansion joint work areas on the following dates (click on maps for larger version):  

See a birdseye view of each weekend closure on this color coded map (pdf 543kb).

__________________________________________________ 

March 29- April 1; April 5-8: Northbound I-5 near Swift Avenue S.  

Two out of five lanes of northbound I-5 will be open from 8 p.m. to midnight, Friday through Sunday. From midnight to 4 a.m. Saturday, Sunday and Monrday, only one lane will remain open. The Swift Avenue S. on-ramp will be closed April 5, 2013 - April 8, 2013.

  • March 29, 2013 - April 1, 2013 - Swift Avenue on-ramp is open
  • April 5, 2013 - April 8, 2013 - Swift Avenue on-ramp is closed
  • The HOV lane is open to all.






___________________________________________________


April 12-15: West Seattle Bridge and 6th Ave. S. to Columbian Way and northbound I-5

The following ramps will be closed from 10 p.m. Friday, April 12 through 5 a.m. Monday, April 15:

  • West Seattle Bridge to Columbian Way
  • West Seattle Bridge to northbound I-5
  • 6th Ave. S. to northbound I-5
  • 6th Ave. S. to Columbian Way


 

May 3-6 West Seattle Bridge and 6th Ave. S. to southbound I-5:

The following ramps will be closed from 10 p.m. Friday, May 3 through 5 a.m. Monday, May 6:

  • West Seattle Bridge to southbound I-5
  • 6th Ave. S. to southbound I-5