I-5 - Ship Canal Bridge Noise Study

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
I-5 Ship Canal Bridge Noise Study,
Seattle

Project Description
WSDOT has been evaluating new and innovative noise-reducing elements to address freeway traffic noise in neighborhoods surrounding the I-5 Ship Canal Bridge. We have identified three potential options for reducing noise: 1) For reverberant and/or reflective noise: Noise-absorptive materials on the ceiling above the I-5 express lanes. 2) For direct noise: Street-level noise walls near the bridge approaches. 3) To reduce noise at the source: Replacement or rehabilitation of the pavement.

Contractor/Consultant
EnviroIssues, Parsons Brinckerhoff

Recent Progress
Team meeting kickoff was held on December 10, 2008. WSDOT stakeholders include the following groups: Bridge Preservation, Bridge and Structures, Bridge Maintenance, Construction Traffic, Design, Environmental (both Air and Noise and Permits sections), Electrical, and Signals.

On December 19, 2007, the team conducted the I-5 Ship Canal Bridge Noise Reduction Project, Contracting Methods Workshop. During the workshop three contracting methods were discussed: design-build, design-bid-build, and Construction Manager General Contractor (CMGC).

Design Construction Impacts
Construction is expected to begin in late spring/summer of 2009. The work will involve the placement of ceiling panels on the I-5 Ship Canal Bridge. Details of the design will be finalized as plan preparation is completed.

Environmental Impacts / Compliance
Shoreline Permit Exemption Received on 12/19/2007. Requests for noise variances for night time work are planned to be submitted to the City of Seattle.

Impacts to Traffic
The work could involve modifications to off-ramps and possible lane restriction on I-5 for night work. Details of these impacts will be finalized as plan preparation is completed.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preconstruction Engineering February 2006 February 2006 Preconstruction Engineering continuing.
Environmental Document Complete January 2009 On track for Spring 2009 constuction start.
Right of Way Certification Complete March 2009 On track for Spring 2009 constuction start.
Advertisement Date April 2009 On track for Spring 2009 constuction start.
Operationally Complete April 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 5.00 100
Right-of-Way 0 0
Construction 0 0
Funded Project Costs 5.0 100

Nickel funds included in above costs

0 0

2005 Transportation Partnership Account

5.0 100

  For more information, go to www.wsdot.wa.gov/projects

Erin Fletcher, WSDOT Project Engineer @ (206) 770-3504 or E-mail: FletchE@wsdot.wa.gov