I-5 - Boeing Access Road to King/Snohomish County Line Pavement Repair - Track Our Progress

9:24 a.m., June 17
Panel-o-meter

Photo of workers replacing concrete panels
View more panel replacement photos

We will replace a total of 440 broken concrete panels on I-5.

Panels replaced to date 434
Total number of panels: 440
Remaining panels: 6

Closures-o-meter

We will work for 100 weeknights and 14 weekends through the summer.

Weeknight closures

Weeknight closures to date: 74
Total weeknight closures: 100
Remaining weeknight closures: 25

Weekend closures

Weekend closures to date: 14
Total weekend closures: 14
Remaining weekend closures: 0