I-5 - Widen I-5 Each Direction From Salmon Creek to I-205 - Complete October 2006

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location
I-5 Salmon Creek Widening – Vancouver

Project Description
This project will widen Interstate 5 from milepost 3.64 to milepost 7.49, from two lanes in both directions to three lanes plus an auxiliary lane between NE 99th Street and NE 134th Street. It will construct two parallel bridges on I-5 over Salmon Creek and a new structure for NE 129th Street over I-5 to accommodate the widening.

Contractor/Consultant
Hamilton Construction Company, Springfield, OR

Recent Progress

Traffic has been shifted onto the new northbound structure and work necessary to widen the southbound lanes is currently underway.  Hamilton Construction has demolished the temporary detour bridge and old southbound bridge and is currently beginning to construct the new southbound bridge. 

Design Construction Impacts

This project has experienced numerous changes and overruns as a result of unforeseen conditions. These unanticipated changes include; the encountering of underground springs, shallow groundwater under the roadway, the relocation of retaining walls due to a natural change that altered the alignment of Tenny Creek, plan revisions to staging, bridge design features, utilities, and the addition of safety features to assist with traffic operation during construction.  Additional construction engineering dollars are necessary because of these changes.  It remains that an estimated $4 million is needed over the current authorizated funding to complete the project based on the already encountered conditions. 

Environmental Impacts / Compliance
WSDOT monitors erosion control and water quality on a daily basis to maintain compliance with the regulatory permits. 

Impacts to Traffic
I-5 northbound and southbound have been shifted to the east (onto the new northbound bridge) to allow for construction of the new southbound bridge.  The northbound and southbound lanes have been reduced to 11-feet wide.  Two lanes of traffic will be maintained in each direction during daylight hours.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised October 2003 May 2003 Completed 5 months in advance of schedule.
Contract Awarded December 2003 July 2003 Completed 5 months in advance of schedule.
Groundbreaking January 2004 August 2003 Completed 5 months in advance of schedule.
Open to Traffic Spring 2007

 

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.3 9.0%
Right-of-Way $1.4 3.8%
Construction $32.0 87.2%
Funded Project Costs $36.7 100%

Nickel funds included in above costs

$32.0 87.2%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Casey Liles, WSDOT Vancouver Area Engineer, at 360-905-1500 or e-mail: swi-5widening@wsdot.wa.gov