Project Title & Location
I-5, SR 532 Interchange Improvements -- Stanwood.
|
Project Description
Replace the temporary traffic signal at the northbound I-5 off ramp with a permanent traffic signal system. Widen SR 532 to allow two westbound lanes and one eastbound lane through the interchange area. Construct a retaining wall and sidewalk on the south side of SR 532 behind the I-5 bridge columns and a new traffic signal at the SR 532 and Old Highway 99 intersection. The project will also add 49 parking spaces to the existing Stanwood Park & Ride lot.
|
|
Contractor/Consultant
Construction started on 6-5-2006
|
|
Recent Progress
Crews finished and opened the expanded P&R lot per scheduled on October 2, 2006, crews also finished paving the third lane of I-5 NB off ramp, finished realignment of Old Highway 99, they also finished sidewalk, curbing and bus pads around the P&R.
|
|
Design Construction Impacts
|
|
Environmental Impacts / Compliance
No significant impacts are anticipated. Storm water will be treated and efforts will be made to minimize wetland impacts.
|
Impacts to Traffic
Lane closures and weekend ramp closures will be required to construct this project. Construction staging is developed in an effort to minimize impacts to traffic. Anticipate a comprehensive public information effort share timing of construction activities and traffic impacts. All work will be completed by summer 2007
|