I-5 - SR 501 Ridgefield Interchange

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
I-5/SR 501 Ridgefield Interchange - Rebuild Interchange

Project Description
This project consists of constructing a new bridge across I-5, reconstructing the I-5 on and off ramps, widening SR 501 between 56th Place and 65th Avenue, and improving the SR 501 intersections at 56th Place and 65th Avenue. The project will reduce congestion and improve traffic flow.

Contractor/Consultant
This project is a partnership between the City of Ridgefield and WSDOT.  HDR Consultant is performing engineering and environmental work.

Recent Progress
90% Plans were submitted in February 2008, and are being reviewed.  The right of way and access plans are complete, and Real Estate Services is beginning the appraisal process; two parcels are in the final stages of acquisition.  The Design Approval Document has been submitted to HQ for review.  Design deviations have been submitted for approval as well.

Design Construction Impacts
The new interchange will be constructed south of the existing bridge.  This will allow for minimized traffic impacts during construction.

Environmental Impacts / Compliance
Wetland impacts will create the need to acquire mitigation sites.  A conceptual mitigation plan has been developed; another conceptual mitigation plan is being developed because of the significant difference between the appraisal amount and the expectations of the property owner.  The environmental documentation (NEPA) was complete in October 2007. 

Impacts to Traffic
Construction staging and traffic control strategies have been developed.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering December 2005 December 2005 Consultant hired in July 2005.
Environmental Documentation Complete December 2008 October 2007 October 2007
Right of Way Certification March 2009 Moved to March 2009 to anticipate a more realistic delivery dependent upon local funding.
Advertisement July 2009 Ad-ready in Summer 2009 to anticipate a more realistic delivery dependent upon local funding.
Operationally Complete November 2011 Moved to November 2011 to anticipate a more realistic delivery dependent upon local funding.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.2 12%
Right-of-Way $0.8 8%
Construction $11.0 80%
Funded Project Costs $13.0 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$10.0 77%

  For more information, go to www.wsdot.wa.gov/projects