Skip Top Navigation

I-5 - South 317th Street HOV Direct Access - November 2004

columns and walls for first level of Federal Way Transit Center
Columns and walls have been built for the first level of Sound Transit's new Federal Way Transit Center to the west of I-5 at S. 317th Street.

workers placing forms in excavation pit for second bridge support
Down in the excavation to the right of the southbound temporary roadway workers place forms for the second support pier for the new S. 317th Street bridge.

pavement crushing equipment near South 320th exit ramp
We've set up a crusher plant near the S. 320th Street exit ramp to crush the old southbound I-5 pavement. We'll recycle the crushed material by using it as a base under the new pavement.

worker standing on catch basin after machine has lowered it into trench
Workers installing a catch basin for the drainage system on the right shoulder of southbound I-5 north of S. 320th Street.

worker driving grading machine on southbound I-5
To prepare the southbound lanes for new pavement, crews are grading the roadway. They're using global positioning satellite (GPS) technology to guide the elevation of the grader blade.

wide shot of southbound I-5 with pavement removed
Crews are done removing the old southbound I-5 pavement and are preparing the roadway for the new pavement.

crews using machinery to drive piles on southbound I-5
Driving piles to shore up the area where the second S. 317th bridge support will be built.  Traffic travels on the temporary roadway beyond the piles.

workers digging ditch with conduit nearby
Workers installing conduit near the S. 320th exit ramp.  The conduit will contain parts of the electrical system that runs ramp meters and traffic cameras.

large pile of pavement rubble near South 320th exit ramp
Rubble from the old southbound I-5 pavement sits in a huge pile near the S. 320th exit ramp.  The crushed rubble will be used as a base under the new pavement.

shovel and dump truck in southbound I-5 work zone in Federal Way
Crews are loading the old southbound I-5 pavement into dump trucks in the work zone between the temporary roadway (left) and the S. 320th exit ramp (right).  The trucks take the rubble to an on-site crusher.

workers installing framework for retaining wall at South 317th in Federal Way
Workers are now building a retaining wall to the north of the S. 317th bridge abutment (notice the abutment toward the upper left of this photo).  You can see the wood forms that will hold the concrete for the wall footing, and some of the steel has been placed for the wall panels.