I-5 - South 317th Street HOV Direct Access - August 2004

pier 1 construction and temporary roadway grading
In the foreground is the rebar shell of one of the two piers that will support the bridge over southbound I-5 at South 317th.  In the background crews are grading for a temporary roadway in the median.  We'll shift traffic to the median this fall to make room for bridge construction.

detention pond O excavation
Crews are excavating for a detention pond on the east side of I-5 just south of Military Road.  When complete, the pond will help capture and clean stormwater runoff.  The project includes four new detention ponds.