WSDOT Projects

text size: T T T

I-5 - South 317th Street HOV Direct Access - Photo History

caption below photo
Sept. 2004 -
Crews built the first S. 317th bridge support on the west side of I-5.

caption below photo
Oct. 2004 -
Southbound I-5 traffic was shifted onto a temporary roadway in the median. This allowed crews to build retaining walls and supports for the S. 317th bridge on the west side of the freeway, next to the permanent southbound lanes.

caption below photo
Feb. 2005 -
Crews set four 100-ton concrete girders in one night for the new S. 317th bridge.

caption below photo
March 2005 -
We improved existing northbound and southbound I-5 pavement using the dowel bar retrofit technique. Dowel bars are inserted into slots cut in the pavement. The bars link the concrete panels and prevent the panels from rubbing against each other and becoming worn.

caption below photo
April 2005 -
Crews installed steel for the bridge deck widening on the northbound I-5 bridge over Military Road. We widened this bridge to accommodate the extension of the HOV lane to S. 320th.

caption below photo
April 2005 - Crews ground the pavement on northbound and southbound I-5 with diamond-tipped saw blades. The right side of this photo shows what the pavement looks like after grinding. This is a safety improvement, as it removes ruts and improves traction.

caption below photo
May 2005 - Crews poured concrete for the deck of the new S. 317th bridge.

caption below photo
July 2005 -
We finished replacing southbound I-5 pavement between Military Road and S. 320th and shifted traffic off the temporary median roadway.

caption below photo
Sept. 2005 -
Crews built a roundabout at the intersection of S. 317th and 28th Ave. S.

caption below photo
October 2005 - Crews installed barrier on the new HOV on and off-ramps in the median. The S. 317th bridge is visible to the upper left in this photo.

caption below photo
Nov. 2005 - Crews built the connections between the HOV ramps and the S. 317th bridge.

caption below photo
Jan. 2006 - Crews placed button pavement markers on the newly-striped HOV ramps.

caption below photo
Feb. 2006 - The new northbound HOV lane and exit ramp at S. 317th, just before crews moved the barrels and opened the interchange to traffic.