I-5 - Rush Road to 13th Street

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
I-5/Rush Road to 13th Street - Chehalis

Project Description
Improves freight mobility, economic development and safety by adding one lane in each direction from Rush Road to 13th Street and constructing an interchange at LaBree Road. There are currently four lanes (two in each direction). There will be six lanes when this project is completed.

Contractor/Consultant
The contract was awarded to Scarsella Brothers, Inc. on May 22, 2007.

Recent Progress
Scarsella Brothers have completed the traffic shift for the first phase of the project to construct lane widening toward the median.  They have also completed the earthwork to realign the local streets near the proposed intersection of La Bree and Bishop Roads.
 

Design Construction Impacts
The project Geotechnical report identified that there will be both short and long term settlements on the new bridges and roadways.  Both over-excavation and replacement of unsuitable material and pre-loading construction methods will be utilized to address the settlements.

Environmental Impacts / Compliance
The North Fork Newaukum wetland bank credits will be used to mitigate wetland impacts.  A hazardous material site has been identified and is located in the southwest quadrant of the LaBree Road interchange. 

During the earthwork for the realignment of the local roads a site requiring a cultural investigation was located.  Upon completion of the investigation it was determined that this discovery was not eligible for National Register listing.

Impacts to Traffic
Construction will be staged and an aggressive public awareness campaign will be used to minimize traffic impacts.  I-5 may be restricted to one lane, each direction at night while staging is completed.  Two lanes will be open in each direction during the daytime and at night as staging allows.   The LaBree Road overcrossing will be closed during construction due to the construction of the new interchange at this location.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering July 2003 July 2003 Complete
Environmental Documentation Complete July 2006 October 2005 Complete
Right of Way Complete December 2006 March 2007 Right of Way certified at level 3.  One parcel remains pending with anticipated completion date September, 2007.
Ad Date January 2007 March 2007 Contract was placed on Ad March 26, 2007 with the bids being opened on May 16, 2007.
Operationally Complete December 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.1 9.8%
Right-of-Way $4.7 9.3% 
Construction $41.6 80.9%
Funded Project Costs $51.4 100%

Nickel funds included in above costs

$47.5 92.6 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Colin Newell, WSDOT Area Engineer, at (360) 740-8600, or e-mail swChehalis@wsdot.wa.gov.