Skip Top Navigation

Budget Information

I-5 - Nooksack River Bridges - Painting

Status

November 2014

  • Work began May 27, 2014. Work is weather-dependent and will take two summers to complete.
  • Work has been completed for 2014. As scheduled, crews will finish painting the bridges in 2015.

Why is WSDOT painting the bridges?
Like a home, car or any other object subjected to year-around weather, steel bridges face the harsh elements like sun, water and chemicals, which age and break down the paint and its ability to protect the steel. They have to be repainted to protect them from the elements.

Removing the old paint, surface rust and then reapplying specialty bridge primer and paint will protect the steel on the structures for roughly 20 years.

These two I-5 bridges carry roughly 41,000 vehicles per day through the Ferndale area. The northbound bridge was built in 1955, and the southbound bridge was built in 1971.

The End Result
Contractor crews will wrap the bridge steel in plastic to collect any falling material, strip off the old paint and apply a new coating of primer and paint. It takes warm and dry weather for this type of work, so crews will work during the best months of summer.

Once complete, the steel structure above and below the roadway on both bridges will be protected from damage by the elements. Painting bridges is an important part of maintaining our valuable infrastructure.

Project Benefits

  • Preservation: Helps preserve the bridge from corrosion while preserving the bridges' structural integrity.
  • Economic: These bridges are an important part of the I-5 corridor. Maintaining the bridges is more cost efficient than replacing them at this time. Maintained properly, they will continue keeping up with the demand of commuter and freight traffic for years to come.

What is the project timeline?

  • March 2014: Project goes to ad
  • April 2014: Project awarded to Dunkin & Bush, Inc.
  • May 2014: Construction begins
  • September 2014 - most painting completed on southbound bridge.
  • Fall 2015: Construction complete

Financial Information

Financial Data for PIN 100595E
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,625
Total $4,625

Total project cost: $4,624,830
Funding source: Pre-Existing Funds (PEF)

How can I get more information?
Contact:
Communications Tom Pearce
15700 Dayton Avenue North
Shoreline, WA 98133
Phone: 206-440-4696
Email: pearcet@wsdot.wa.gov    

Project Engineer Chris Damitio 
460 Stuart Road
Bellingham, WA 98226
360-788-7400
Email: DamitiC@wsdot.wa.gov 

back to top